Do not misuse constraints

Do not misuse constraints

Do not misuse constraints As constraints will limit the dynamicity, your challenge is to avoid these as much as possible – do not misuse constraints. In some cases though you will need them. Consider for instance the following situations: [divider] [action_call text=”Microsoft Project Introduction Course” button_url=”https://members.ms-project-elearning.com/vsl-order-form” button_text=”Purchase Now for only 0.99 USD”] [divider] Place the roof, once the supporting walls are …

How to create constraints

How to create constraints

Constraints are created when: Dates are typed into the start or finish columns or If you double click on a task and change the constraint type in the Advanced tab of the task information window. [divider] [action_call text=”Microsoft Project Introduction Course” button_url=”https://members.ms-project-elearning.com/vsl-order-form” button_text=”Purchase Now for only 0.99 USD”] [divider] If a task has a constraint date attached to it you will immediately see a …

How to remove a constraint?

How to remove a constraint?

I bet that if you would open a random schedule, you would see all little calendars in front of the tasks. These appear when you have entered a start or finish date manually, and will add a serious amount of manual labour for you when you update your schedule. So you want to have as little constraints as possible and …