- This task cannot start earlier than July 1, 2016
- This task cannot finish later than August 23, 2016
- This task must start on January 1, 2017
Using constraints, you can control the start or finish dates of important tasks. It is a useful tool to be able to easily reschedule the project because when you put a constraint on a task in a linked network of tasks, it will effect the whole chain of tasks. MS Project automatically assigns the As Soon As Possible constraint (which actually is not a restriction) when you enter a task (when planning from start date). You should set other constraints only when necessary, because:
- Constraints will usually decrease the level of schedule flexibility of tasks
- As the amount of task flexibility decreases also the amount of dynamic behavior of the schedule gets lost